Is the Antminer S19k Pro 120T (reference) profitable?

Bitmain · 2022 · Air-cooled · 120 TH/s · 2,760 W · 23 J/TH

Saved input sources

Based on network data from Oct 14, 2026, 05:15:04 UTC

Bitcoin price

$83,466 · Hourly price collection (saved snapshot)

Updated Oct 14, 2026, 05:15:04 UTC

Network difficulty

132.72 T · mempool.space (saved snapshot)

Updated Oct 14, 2026, 05:15:04 UTC

Block subsidy

3.125 BTC · Bitcoin protocol

Effective since Apr 20, 2024

Fee revenue per block

0.0179 BTC (7-day) · 0.0173 BTC (24-hour) · mempool.space reward stats (saved snapshot)

Updated Oct 14, 2026, 05:15:04 UTC

Network snapshot

Block 971,354 · 950.0 EH/s (difficulty-implied)

Hashrate derived from current difficulty via mempool.space (saved snapshot)

No. At $0.075/kWh, BTC at $83,466 and difficulty 132.72 T, the Antminer S19k Pro 120T (reference) earns $4.58/day but power costs $4.87/day, so it loses $0.29/day. It needs electricity below $0.071/kWh to break even.

Net profit / day
−$0.29
−$9 / month
Revenue / day
$4.58
5490 sats / day
Power / day
$4.87
$0.075/kWh
Simple payback
No payback
on $300
Shutdown BTC price
$88,677
today's difficulty
Shutdown after halving
$176,348
≈ Apr 2028 (estimated)
Break-even electricity
$0.071/kWh
today
Break-even after halving
$0.035/kWh
same price & difficulty

Profit by electricity price

ElectricityPower / dayNet profit / dayNet profit / monthSimple payback
$0.030/kWh$1.95$2.64$803.7 months
$0.050/kWh$3.25$1.34$417.4 months
$0.060/kWh$3.89$0.69$2114.3 months
$0.075/kWh$4.87−$0.29−$9No payback
$0.090/kWh$5.84−$1.26−$38No payback
$0.120/kWh$7.79−$3.21−$98No payback

Specifications and price

ManufacturerBitmain
Hashrate120 TH/s
Power2,760 W
Efficiency23 J/TH
CoolingAir
Observed price$300 (secondary-market median)
Price per TH$2.50/TH
Est. resale after 24 months$150
Status / channelUsed · Secondary market

Prices are point-in-time observations from September 24, 2026, not quotes.

Similar air-cooled machines

MachineTH/sJ/THPriceNet profit / day
Antminer S19j XP 151T15121.5$453$0.04
Antminer S19 XP 141T14121.5$298$0.04
WhatsMiner M6016019.9$1,280$0.49
WhatsMiner M60S18418.5$1,656$1.02

Questions about the Antminer S19k Pro 120T (reference)

Is the Antminer S19k Pro 120T (reference) profitable?

No. At $0.075/kWh, BTC at $83,466 and difficulty 132.72 T, the Antminer S19k Pro 120T (reference) earns $4.58/day but power costs $4.87/day, so it loses $0.29/day. It needs electricity below $0.071/kWh to break even.

At what Bitcoin price should the Antminer S19k Pro 120T (reference) be turned off?

At $0.075/kWh it stops covering its power cost below about $88,677 per BTC at today's difficulty. After the next halving, ≈ Apr 2028 (estimated), that rises to about $176,348 at the same difficulty.

What electricity price does the Antminer S19k Pro 120T (reference) need to be profitable?

Below about $0.071/kWh at today's Bitcoin price and difficulty, falling to about $0.035/kWh after the halving.

How efficient is the Antminer S19k Pro 120T (reference)?

23 J/TH: 120 TH/s at 2,760 W, air-cooled, released 2022.

Assumptions: FPPS payout with the 7-day average transaction fees per block, 2% pool fee, 98% uptime, no facility overhead, taxes or financing. Post-halving figures halve the block subsidy at today's Bitcoin price and difficulty. These are snapshots, not forecasts.